Lithium brine processing in Chile: the Salar de Atacama in 2026

Home Lithium brine processing in Chile: the Salar de Atacama in 2026

Chile’s commercial lithium brine processing takes place at the Salar de Atacama, where two operators pump brine: NovaAndino Litio, the joint venture Codelco and SQM formed on 27 December 2025, and Albemarle. Lithium is reserved to the State, so a new producer needs a special lithium operating contract (CEOL) or a partnership with a state company, not an ordinary mining concession. The government that took office on 11 March 2026 is more openly pro-investment, but the state-led model set out in the 2023 National Lithium Strategy is still the legal route.

For anyone designing, financing or supplying an Atacama brine process, two 2026 developments matter more than the politics. NovaAndino’s brine extraction is capped at 822 litres per second from 2028, and since 12 May 2026 its gross extraction counts as net, so pumping extra brine and reinjecting the surplus no longer buys headroom. Albemarle, for its part, has filed a US$3.1 billion plan to move its operation to direct lithium extraction (DLE). This page sets out where things stand, with dates and sources, and what the new limits mean for recovery, water and residues.

We are Brine Consulting, an independent industrial water advisory firm in Amsterdam. We sell no treatment equipment, DLE or otherwise, so our only interest in an Atacama process is whether its brine, freshwater and recovery numbers hold up. We advise operators, technology developers and investors on Chilean salar projects remotely or through a defined engagement.

Status at November 2026: what has changed and what has not

Date What happened Source
13 Oct 2026 Three CEOLs (Ollagüe, Ascotán, Laguna Verde) are with the Comptroller General; two more are being prepared. The government plans to remove the Chilean Nuclear Energy Commission’s (CCHEN) role in lithium permits during 2026. Minería y Futuro
16 Sep 2026 Economy and Mining Minister Daniel Mas says the government wants private companies to lead lithium investment and invites them to partner with Codelco. Emol
Aug 2026 First CEOL signed with a private company acting alone: Quiborax, for up to 20,000 t of lithium carbonate recovered from mining residues in Arica y Parinacota. Minería y Futuro
11 May 2026 Environmental approval (RCA 182/2026) issued for NovaAndino’s “Plan de Reducción de Extracciones en el Salar de Atacama”, after a unanimous vote of the Antofagasta evaluation commission reported on 29 April. SEA notice, Reporte Minero
25 Mar 2026 Reporte Minero reports that Albemarle has filed an environmental impact study for its US$3.1 billion “Transición hacia Extracción Directa de Litio (DLE)” project. Reporte Minero
12 Mar 2026 The Environment Ministry withdraws 43 decrees from the Comptroller’s review, including the six that would have created the protected salt flat network in the Atacama Region. They were not among the decrees resubmitted by June 2026 and were still on hold in September 2026, when 34 of the 43 had yet to be resubmitted. Chile Sustentable, June 2026, El Desconcierto, 19 Sep 2026
11 Mar 2026 José Antonio Kast takes office and places economy and mining under one minister. Gibson Dunn, 23 Mar 2026
29 Jan 2026 Outgoing President Boric signs decrees grouping ten Atacama Region salt flats and high Andean lagoons into six protected areas. Radio Universidad de Chile
27 Dec 2025 Nova Andino Litio SpA is formed by merging Codelco’s Minera Tarar and SQM Salar. It holds the Salar de Atacama lithium business to 2060; SQM manages it until 2030 and Codelco from 2031. Codelco, partnership site
31 May 2024 Codelco and SQM sign their partnership agreement. Codelco
Apr 2023 National Lithium Strategy announced: a state-led model, Codelco to represent the State in the Salar de Atacama, a protected salt flat network and low-impact technologies where salt flats are already exploited. InvestChile

What has not changed is the legal base. Decree Law 2886 reserves lithium to the State, lithium is still a “material of nuclear interest” whose sales and exports need CCHEN authorisation, and access runs through state companies or CEOLs (Gibson Dunn, 23 March 2026). None of the sources we reviewed, up to early November 2026, reports a law or decree replacing the 2023 strategy. The CCHEN change, if it happens, needs a change in the law; until then, build the CCHEN step into any schedule for selling Chilean lithium.

How Atacama brine becomes lithium chemicals today

The incumbent route is pumping and solar evaporation. SQM’s latest technical report summary, dated 13 April 2026, describes it like this (SEC filing):

  • Feed brine. Brine is pumped from the salar nucleus. Mean concentrations across the samples are 0.16 wt% lithium and 1.7 wt% potassium.

  • Evaporation. Sequential solar evaporation concentrates the brine. Potassium salts are harvested and treated, and the lithium concentrate is processed at the Carmen lithium chemical plant near Antofagasta.

  • Products. Lithium carbonate capacity reached 210,000 t a year in 2025. Lithium hydroxide capacity of 40,000 t a year is being raised to 100,000 t a year, expected by the end of 2026.

  • Recovery. Average process efficiency is about 49% for lithium and 76% for potassium. Roughly half the lithium pumped out of the salar does not reach a product.

  • Water. Process water comes from wells in the alluvial aquifer on the eastern edge of the salar. The 2026 permit caps total extraction from those wells at 120 L/s (Reporte Minero).

The brine is also getting harder to process. A review published in Minerals Engineering in September 2026 reports lithium at about 1,835 mg/L, with the magnesium to lithium ratio rising from about 6.4 to about 8 and the sulfate to calcium ratio from about 2.4 to about 15 (Toro et al., 2026). In practice, higher ratios mean more competing salts in the ponds, which makes the same lithium recovery harder to hold.

The 822 L/s cap, and why “gross equals net” matters

When SQM filed its extraction reduction plan in 2022, the target was stated as net extraction: brine pumped minus brine reinjected. The Consejo de Pueblos Atacameños objected that gross pumping could stay the same while reinjection rose (Terram, 12 May 2022).

The approved version closes that gap. SQM’s public brine monitor states that from 12 May 2026, under the new RCA 182/2026, gross extraction is treated as equivalent to net extraction, falling to 822 L/s in 2028 (SQM brine monitor). That is about half the previously authorised rate and holds for the life of the operation (Reporte Minero, 29 April 2026).

The practical consequence: NovaAndino cannot grow by pumping more and returning the surplus. Growth has to come from recovering more lithium from each litre it pumps. Albemarle’s DLE filing, by contrast, is framed as a cut in net extraction, with spent brine returned to the salar. When you compare the two operations, or a vendor’s claims about either, check which basis each number uses.

What 822 L/s can produce: a recovery check

This is a hypothetical calculation to show the scale of the problem, not a forecast for any operator.

Assumptions: 822 L/s pumped continuously for 365 days; lithium at 1,835 mg/L (the 2026 review figure above); 5.323 t of lithium carbonate equivalent (LCE) per tonne of lithium; process efficiency of 49% (SQM’s reported average).

  1. Lithium pumped: 822 L/s × 1.835 g/L = about 1,508 g/s, or about 47,600 t of lithium a year.

  2. In carbonate terms: 47,600 × 5.323 = about 253,000 t LCE a year contained in the brine.

  3. At 49% recovery: about 124,000 t LCE a year.

  4. To supply 210,000 t a year of carbonate capacity from this brine alone, overall recovery would have to reach about 83% (210,000 ÷ 253,000).

The partnership’s website, which is undated and appears to have been written around 2024, projects 280,000 to 300,000 t LCE a year from 2031 to 2060 without increasing brine extraction or inland water use (partnership site). At our assumptions that is 111% to 118% of the lithium contained in 822 L/s of brine, which raises a fair question: what closes the gap? The projection appears to predate the 2026 permit and may rest on inputs that differ from ours, such as well-by-well grade, salts already in the ponds, or a different extraction basis. Those inputs are not in the public documents we reviewed. Treat the figure as something to test, and ask for the grade, extraction schedule and recovery curve behind it.

You can repeat this check with your own flows and grades in our brine mass balance calculator.

DLE in the Atacama: what it can and cannot fix

Albemarle’s filing, as reported by Reporte Minero on 25 March 2026, describes a modular DLE plant of up to six trains of 50 L/s each, 300 L/s in total. Construction would start in the second half of 2028 and run for about nine years. Treated brine, lower in lithium, would go back to a reincorporation zone at up to 90%. Brine extraction would fall from the current 442 L/s to 342 L/s in a first stage, and to 142 L/s net with all three modules running (Reporte Minero).

The September 2026 review in Minerals Engineering is a useful counterweight to vendor enthusiasm (Toro et al., 2026). Its authors propose a hybrid: keep optimised solar evaporation, add DLE at selected points, then recover water and reinject under control. They make three points worth putting to any DLE proposal:

  • Reinjection is unproven at scale here. The review states that reinjection is not a mature, field-validated practice in Andean salar basins.

  • DLE does not automatically save water. Some DLE routes need more freshwater than evaporation does. In the Atacama that water competes with the 120 L/s well cap.

  • Carbon depends on the power source. The review credits solar evaporation with a comparatively low carbon footprint. A DLE circuit’s footprint swings widely with the energy supply behind it.

Before backing a DLE design for an Atacama brine, we would want to see the freshwater demand per tonne of product and where that water comes from; the composition of the returned brine compared with the brine it displaces; how reinjection performance will be monitored; and where the eluate, regeneration and wash streams end up.

“How much water does lithium use?” Separate brine from freshwater

Figures quoted online for water per tonne of lithium often add pumped brine and freshwater together. They behave differently. Brine is not usable water, yet it is part of the basin’s water system: researchers writing in Desalination in 2021 argue that brine is “undeniably a type of water” for exactly this reason (Ejeian et al., 2021).

A 2024 water footprint study of Atacama lithium found that brine production dominates the result: 326 of 442 m³ world equivalents per tonne of product under the AWARE method. It found the final chemical stages had minimal water scarcity impact, mainly because they use desalinated water (Marinova et al., 2024). For any Atacama project, report brine extraction, freshwater extraction and evaporation losses as separate lines. Combined figures hide the freshwater number, which is the one under the tightest cap.

Checks before you commit to an Atacama brine project

  1. Which permit basis applies? Is your extraction limit gross or net, and what counts as reinjection?

  2. What is the brine, by well and over time? Lithium grade, Mg/Li and SO4/Ca ratios, and how they have trended. Check every lab analysis for charge balance with our Water Analysis Validator before it goes into a design basis.

  3. What recovery is assumed, and from what evidence? Pond yields measured in the field, or pilot data from a different brine?

  4. Where does the freshwater come from? Within which permitted cap, and what happens if that cap tightens?

  5. What leaves the process? Harvested salts, spent brine, eluates and wastewater, with a destination and owner for each.

  6. What is the contract route? CEOL, partnership with a state company or offtake from an incumbent, and where the CCHEN authorisation sits in the schedule.

  7. Is the salar protected or proposed for protection? The Atacama Region decrees were withdrawn, not cancelled, and could return.

  8. What does indigenous consultation require? It is part of CEOL processes and of the Codelco and SQM arrangement, and it takes time.

The Atacama is not a template for other salars

Projects in Argentina’s salars work under different ownership and permitting rules. See our page on Argentina lithium brine and DLE water management. For the chemistry and viability basics behind any brine, read lithium from brine. For the wastewater and residues from refining lithium chemicals, see lithium refinery wastewater and ZLD. For non-lithium brine, ZLD and water reuse at other Chilean industrial sites, see our Chile brine valorization and ZLD page.

Where an independent brine review fits

The useful moment for an outside review of an Atacama project is before a recovery or freshwater figure is locked into a design basis, a financing model or an offtake. On Chilean lithium brine that work can cover:

  • reviewing brine and water mass balances, including gross and net extraction accounting

  • testing recovery and water claims in DLE and evaporation proposals against the brine data

  • defining what happens to spent brine, salts and process wastewater

  • technical due diligence for lenders, investors and offtakers

See our advisory and due diligence and brine resource recovery services.

Questions about Chilean lithium brine

Does the 822 L/s cap apply to Albemarle? No. It sits in NovaAndino’s permit. Albemarle’s March 2026 filing, as reported by Reporte Minero, puts its current brine extraction at 442 L/s.

Is DLE mandatory in Chile? The 2023 strategy calls for low-environmental-impact technologies in salt flats already being exploited. The summaries we reviewed do not name a specific technology.

What happened to the protected salt flat network? The six Atacama Region decrees signed in January 2026 were withdrawn from the Comptroller’s review on 12 March 2026 and were still on hold in September 2026. Six further decrees covering salt flats in the Antofagasta Region were approved by the ministers’ committee but never signed or sent for review.

Talk to us before the design basis is fixed

If you hold a recovery or freshwater figure for an Atacama brine process and are not sure which extraction basis or brine grade it rests on, that is a good question for a scoping call. You can also send us your project details with the documents behind the figure.

Written by the Brine Consulting advisory team. The Brine Consulting advisory practice includes Dr. Tijjani El-Badawy, Specialist, Produced Water, Critical Minerals & Circular Economy, an interdisciplinary water, energy and sustainability specialist with expertise in produced water desalination and critical mineral recovery, and Wendy Garcia, PhD, a senior electromembrane R&D and technology development expert with more than 15 years of experience in electrodialysis, bipolar membrane systems, brine treatment and resource recovery. Meet our experts.