On a UAE industrial site, the decision that shapes a wastewater project is rarely the treatment technology. It is where the treated water and the concentrate are allowed to go, and which authority says so. That answer changes from one emirate to the next, and in Dubai it can change from one zone to the next.
This page sets out who regulates industrial discharges, the Abu Dhabi sewer limits that decide whether RO reject can go to drain, and the brine routes left when it cannot. Brine Consulting is an independent industrial water advisory firm in Amsterdam. Because we sell no treatment equipment, our answer to where the reject should go is not tied to a plant we want to supply. We advise UAE sites remotely or through a defined engagement on brine management, water reuse, and minimal and zero liquid discharge.
Who regulates industrial discharge, emirate by emirate
A federal law sets the baseline. Federal Law No. 24 of 1999 bars industrial, commercial and other premises from discarding untreated liquids that may pollute the water environment (Article 35). Coastal establishments that discharge need an environmental impact study and their own treatment units (Article 36), and the executive regulation sets discharge standards and lists persistent pollutants that may not go to sea (Article 37). Project owners must monitor what they discharge, keep the records and report the results (Article 7).
The permits you actually apply for are local:
| Where the site is | Who you deal with | What the rule requires |
|---|---|---|
| Abu Dhabi, discharge to sewer | Department of Energy rules; consent issued by the licensed sewerage collection company | A Trade Effluent Consent for any trade effluent sent to a sewer, valid for up to three years, with numeric limits in Schedule A (Trade Effluent Control Regulations 2022) |
| Dubai, municipal areas | Dubai Municipality | Industrial wastewater may enter the public sewer only after the Municipality has verified it meets its standards (Article 8). Building a treatment plant needs written approval (Article 6). Dubai Municipality still lists the order, amended in 2005 and 2006, as current legislation (Local Order No. 8 of 2002) |
| Dubai, new or modified industrial and infrastructure projects | Dubai Municipality Environmental Sustainability Department | Environmental Clearance after an impact assessment. Any outfall carrying brine, hypersaline or thermal effluent needs a full EIA report, with no size threshold (EC guidance, 2024) |
| Dubai areas under Trakhees (land owned by the Ports, Customs and Free Zone Corporation and Dubai World, such as Dubai Maritime City and Nakheel developments) | Trakhees Environment, Health and Safety | Separate permits for harbour discharge of treated wastewater, irrigation with treated wastewater and groundwater discharge, with the relevant analysis, for example of irrigation water or harbour discharge, from an EIAC-accredited laboratory (Trakhees procedure CP-02, Nov 2024; about Trakhees) |
| Sharjah | Sharjah Municipality | Issues environmental permits and inspects industrial facilities for their environmental and waste disposal permits (Sharjah 24, Feb 2022) |
| Ras Al Khaimah | Environment Protection and Development Authority (EPDA) | Environmental permits for industrial establishments (EPDA), and an approval framework agreed with RAKEZ for cement, chemical and general industrial activities (RAKEZ and EPDA) |
In Dubai, check the site’s address against the Trakhees areas before anything else, because it decides which permit system you are in. In Ajman, Umm Al Quwain and Fujairah, confirm the competent authority with the local municipality before design starts.
The Abu Dhabi sewer limits that decide where RO reject goes
Abu Dhabi publishes its sewer limits for trade effluent in one regulation. The 2022 edition, in force since 1 January 2022, replaced the 2010 regulations and is the edition the Department of Energy publishes as of November 2026. Its Schedule A sets these maximums, among others:
| Parameter | Maximum for discharge to sewer |
|---|---|
| Total dissolved solids | 2,000 mg/l |
| Chloride | 1,000 mg/l |
| Sulphate | 1,000 mg/l |
| COD | 1,000 mg/l |
| Suspended solids | 500 mg/l |
| Oil and grease (hydrocarbon) | 60 mg/l |
| Temperature | 45 °C |
| pH | above 6 and below 9 |
The collection company may set stricter limits in your consent (clause 3.2.2). The salt limits are the ones that catch reverse osmosis projects, because an RO unit does not remove salt from the site. It concentrates it into a smaller stream.
A worked example (hypothetical feed). An RO unit treats water with 800 mg/l TDS and 250 mg/l chloride. With near-complete salt rejection, the reject is stronger than the feed by a factor of roughly 1 / (1 – recovery).
| RO recovery | Concentration factor | Reject TDS (mg/l) | Reject chloride (mg/l) | Against Schedule A |
|---|---|---|---|---|
| 50% | 2.0 | 1,600 | 500 | Within both limits |
| 60% | 2.5 | 2,000 | 625 | At the TDS limit |
| 75% | 4.0 | 3,200 | 1,000 | Over TDS, at the chloride limit |
| 85% | 6.7 | 5,300 | 1,670 | Over both |
On this feed the sewer route closes at about 60% recovery. Every step up in recovery saves fresh water and pushes the reject further over the limit, so the water-saving case and the discharge consent pull in opposite directions. Decide the reject route at the same time as the recovery target, not after the RO has been ordered. Real membranes pass a little salt, so actual reject is slightly weaker than these figures; run your own analysis through our Brine Concentration Factor Calculator.
Two things in the regulations are easy to miss. First, the consent fixes the discharge point and the allowable concentrations (clause 5.4.2), so whether reject may be blended with other site effluent before that point is a question for the consent, not an assumption to build into a design. Second, monitoring can land on the site. The collection company may require you to install a sampling point and meters for discharge volume and composition, and can mandate online monitoring where a discharge carries a high risk (clauses 6.2.1, 6.3.1 and 6.3.3). Sampling that the consent assigns to you is at your own cost, and analysis must come from an ISO/IEC 17025 accredited laboratory. The collection company may also require you to keep discharge records for at least 10 years (clause 6.6.4). Any entity that fails to comply with the regulations can face a fine of not less than AED 250,000, and the Department of Energy can impose an administrative fine of up to AED 10 million.
Where can brine go from a UAE site?
A saline stream from a UAE site has five possible routes. Each has its own rule, and in our view the rule usually decides the cost before the technology does.
| Route | What applies | What to check first |
|---|---|---|
| Public sewer | Abu Dhabi: Trade Effluent Consent and Schedule A. Dubai: Municipality verification under Local Order No. 8 of 2002 | Whether the reject meets the salt limits at the recovery you want |
| Sea or harbour outfall | Federal Law No. 24 of 1999, Article 36. Dubai: a full EIA report for any brine outfall. Trakhees areas: a harbour discharge permit | Time and cost of the impact assessment, and the federal list of pollutants barred from the sea |
| Discharge to soil or aquifer | Dubai: an RO plant that discharges to soil, pumps into an aquifer or abstracts saline groundwater needs a full EIA report | Whether this route is realistic for your site at all |
| Tanker to a licensed facility | Abu Dhabi: tankered trade effluent only at a permitted, designated discharge point (clause 3.1.1(e)). Dubai: disposing of wastewater at locations the authority has not designated is prohibited, and reported penalties include vehicle impoundment and an AED 100,000 fine (Khaleej Times, Aug 2026) | A recurring haulage bill, and dependence on another party’s capacity |
| Reduce or eliminate on site (minimal or zero liquid discharge) | Your own environmental permit; the residual salt becomes a solid waste stream | Mass balance, energy use, and how the solids will be classified and disposed of |
Dubai Municipality’s Jebel Ali hazardous waste treatment facility, commissioned in 2018, treats 600 m³ a day of industrial liquid waste containing oils, heavy metals, acids and alkalis. Reverse osmosis lets the Municipality reuse almost 75% of the treated water for irrigation, and the RO reject goes to evaporation ponds (Middle East Construction News). So at least one endpoint for industrial liquid waste in Dubai is itself a zero liquid discharge plant.
For a deeper look at the disposal side, see our guide chapter on evaluating the disposal endpoint first and our article on RO reject water. For seawater desalination plants and their outfalls, our page on desalination brine disposal in the UAE covers the Gulf and Gulf of Oman discharge rules.
Why the UAE context pushes industry toward reuse
Desalination carries much of the UAE’s water supply, and national policy now pushes treated wastewater back into use.
Desalination supplies about 42% of the country’s total water requirement, from around 70 major plants (as of November 2026), according to the UAE government portal.
The UAE Water Security Strategy 2036 aims to cut total water demand by 21% and to raise recycling and safe reuse of treated water to 95%, according to the same UAE government portal.
For a plant engineer, the reuse target matters most. If your site switches from desalinated water to treated effluent as its feed, the feed chemistry changes, and so do the RO recovery you can reach and the composition of the reject. A reuse project and a brine plan are the same project. Our article on industrial water reuse systems covers the reuse side in more depth, and our page on industrial water reuse in the UAE sets out recycled water prices and cooling water rules by emirate.
When is a ZLD feasibility study worth commissioning?
Zero liquid discharge sits at the expensive end of the range, and in our view minimal liquid discharge often gets most of the benefit for less. A study is worth paying for when one or more of these is true:
The reject cannot meet sewer limits at the recovery you need, and no outfall is available or permitted.
Tanker volumes are growing and the haulage bill is now a fixed operating cost.
An Abu Dhabi consent is coming up for renewal, or a new production line will change what you discharge.
A Dubai project is going through Environmental Clearance and the discharge route will decide the level of assessment.
The site or its owner has a water reduction target that discharge to sewer cannot meet.
In our view a good study settles the endpoint first, then builds the whole-site water balance, checks the water characterisation and only then compares treatment trains. Our MLD vs ZLD screener gives a first indication, and our guide to what a ZLD feasibility study covers sets out the scope. The comparison of minimum liquid discharge and ZLD explains when the cheaper option is enough.
How we work with UAE sites
We advise UAE sites remotely and by engagement, working from the site data the client shares. The work covers ZLD and MLD feasibility studies, RO reject management, technology screening before suppliers are invited, review of vendor proposals and technical due diligence. If you are at the stage of comparing suppliers, our independent guide to choosing a water treatment company in the UAE and our ZLD vendor proposal checklist are the places to start. For Saudi Arabia and the rest of the Gulf, see our Middle East overview.
The UAE is three hours ahead of Amsterdam in winter and two hours ahead in summer, so a morning call in Amsterdam falls in the UAE working day.
Questions UAE sites ask
Does UAE law require zero liquid discharge? We found no general UAE rule that makes ZLD mandatory for industrial sites. Dubai’s impact assessment guidance lists zero discharge to the aquatic environment as a principle to aim for, and a specific permit or project approval can impose it. In our view, ZLD becomes the answer only when no permitted endpoint is left at a cost the site can carry.
How long does an Abu Dhabi trade effluent consent last? Up to three years. The collection company must decide on an application within 60 days and give reasons if it refuses.
Our plant is in a Dubai free zone. Who regulates our wastewater? It depends on the land. Areas owned by the Ports, Customs and Free Zone Corporation and Dubai World fall under Trakhees; elsewhere in Dubai, Dubai Municipality issues the approvals. Confirm with your zone authority before you apply.
Talk to us before the reject route is fixed
If you are about to fix an RO recovery target, renew an Abu Dhabi consent or settle the discharge route in a Dubai clearance, send us the water analysis and the permit conditions you already have, or email christos@brineconsulting.com. In a call we can say which reject routes look open and what a study would still need to settle. Book a scoping call or send us your project details.
Written by the Brine Consulting advisory team. The Brine Consulting advisory practice includes Ghazi Ozair, a senior desalination and environmental water expert with more than 45 years of global experience across membrane and thermal desalination, wastewater treatment, produced water and marine protection, and Edwin Muller, a senior industrial water expert with more than 25 years of experience across refineries, petrochemicals, power generation, hydrogen and ammonia. Meet our experts.