In Argentina, a lithium brine project’s water is permitted by the province, and usually in pieces. The Mining Code’s environmental title makes provincial authorities responsible for approving each project’s environmental impact report and requires the approval to be updated at least every two years (Ley 24.585, 1995). Fresh water is granted separately under each province’s water law. When several projects share one basin, those separate approvals can add up to something nobody assessed, which is what a Catamarca court said in 2024.
Direct lithium extraction (DLE) shifts the water question rather than removing it. It cuts the brine lost to evaporation ponds, but it needs fresh water for its own process and produces spent brine that has to go somewhere. This page sets out how those streams are regulated in Catamarca, Salta and Jujuy, what the Hombre Muerto case changed, and what a defensible water case looks like. For the extraction methods themselves, see our post on how lithium is extracted from brine.
Three water streams, three different questions
A DLE plant on a salar moves three kinds of water, and each meets a different part of the rules.
| Stream | What it is | How it is regulated | What to measure |
|---|---|---|---|
| Brine | Lithium-bearing brine pumped from the salar through production wells | Part of the mining project: assessed in the environmental impact report (IIA) and approved by a Declaration of Environmental Impact (DIA) from the provincial mining authority, updated at most every two years (Ley 24.585, arts. 5 to 11) | Pumping rates, drawdown, changes in brine chemistry over time |
| Fresh water | Water for eluting the DLE media, washing, reagents, utilities and camp | A water concession under the provincial water law, handled by the province’s water authority (see the table below) | Volume per tonne of product by use, source, and share of basin recharge |
| Spent brine and process effluents | Lithium-depleted brine after DLE, rejects from concentrating the eluate, plant effluents | Assessed in the IIA; water laws also restrict how used water is returned (Salta, for example) | Where it goes (reinjection wells, salar surface, ponds), its chemistry, and its effect on the brine body |
The split matters because fresh water is where the conflicts are. A study led by University of Massachusetts hydrologist Dan Corkran, published in September 2025 and covering a wetland at the Salar del Hombre Muerto, found that pumping fresh water near a basin’s edge affects wetlands far more than pumping denser brine (Water Resources Research, 2025; university summary). Climate Home News reported in October 2025 that Corkran’s research linked a 90% reduction in wetland vegetation to a lithium plant’s freshwater extraction, and quoted his view that fresh water and brine cannot be treated as equivalent in a water footprint (Climate Home News). The same article reported that a 2023 review of 57 published DLE articles (Vera et al., Nature Reviews Earth & Environment) found about a quarter reporting significantly higher freshwater use than conventional brine operations, in some cases more than ten times higher. DLE can save water, but only a project-specific balance shows whether it does.
Who permits water for a lithium project in each province?
Most of Argentina’s lithium brine projects sit in Catamarca, Salta and Jujuy. Argentina had 56 lithium projects at some stage of development in mid-2026, seven of them in operation, according to national mining directorate figures reported by Panorama Minero (July 2026).
| Province | Water law | Environmental route for lithium | Points to note |
|---|---|---|---|
| Catamarca | Decreto Ley 2.577 of 22 May 1973: industrial uses, including mining establishments, need a concession; the Dirección de Administración de Aguas processes applications and the provincial executive grants them | IIA and DIA through the Ministry of Mining’s Dirección Provincial de Gestión Ambiental Minera; water permits sit with a separate ministry | The 2024 Hombre Muerto ruling and the cumulative impact study (next section) |
| Salta | Water Code, Ley 7.017 (1998): mining water needs a concession (art. 100); industrial concessions above 300 litres per second need a special law (art. 86); water used in mining must be returned without harm to third parties or the environment (art. 105) | IIA and DIA under Ley 24.585 through the provincial mining authority | 300 L/s is about 25,900 m3 a day. If a project’s water is classed as industrial use, demand near that level means a legislative step, so check which article your concession falls under |
| Jujuy | Provincial Water Code; a 2019 study by the Argentine NGO FARN notes it requires mining water to be returned without affecting third parties and water access to be quantified and controlled (FARN, 2019) | Lithium deposits declared a strategic resource, with an expert committee review of lithium projects added (Decree 7592/2011, summary by Marval); the general environmental law 5063 is now regulated by Decree 7751/2023, published 27 February 2023, which revoked Decree 5772/2010 (Marval) | FARN describes the Olaroz-Cauchari basin as closed, at about 4,300 m, with year-round water stress |
Procedures change and are applied differently project by project, so confirm the current route with the provincial authorities before you commit a schedule to it. Two 2026 changes are worth tracking. The three provinces agreed a technical assistance programme with the Consejo Federal de Inversiones for a joint Región Minera del Litio (Salta Decree 266, published 6 May 2026, per Marval). Nationally, Ley 27.804, promulgated in April 2026, replaced the 2010 Glacier Law and lets a province ask for glaciers or periglacial landforms that do not serve a public-interest water function to be taken off the national inventory (Bichos de Campo); court challenges to it were still running in mid-2026. If your fresh water comes from a high Andean catchment, check how your province applies it.
What the Hombre Muerto case changed
The Salar del Hombre Muerto and the Río Los Patos sub-basin, in Catamarca, show what happens when water approvals are made one project at a time.
13 March 2024. In Guitián, Román E. c/ Poder Ejecutivo Nacional y otro, the Corte de Justicia de Catamarca ordered the provincial mining environmental authority to carry out a cumulative and integral environmental impact study of lithium mining in the Río Los Patos and Salar del Hombre Muerto area. The court noted that projects, including Fénix, Sal de Vida and Sal de Oro, had been assessed individually and that water permits were handled by a separate ministry. As a precaution, no new permits or environmental approvals were to be granted in the area until the study was complete (ruling summary, Microjuris).
September 2024 to May 2025. The study was carried out by the consultancy LIPAT with funding from the Consejo Federal de Inversiones. It was presented in July 2025 and ends in a cumulative impact management plan with seven monitoring and control programmes (El Ancasti, October 2025).
Reported 31 March 2026. The court lifted the precautionary measure, finding no proof of current environmental damage, and stated that the monitoring, evaluation and control mechanisms in current law must stay in place, along with the hydrological studies and follow-up recommended in the government’s report (El Ancasti, 31 March 2026).
The lifting may not be the last word. iProfesional reported on 2 June 2026 that two judges had dissented, that the study’s full contents had not been made public, and that the Comunidad Originaria Atacameños del Altiplano had appealed (iProfesional). The lesson we draw for any project sharing a basin, in Catamarca or elsewhere: your water case will be read alongside your neighbours’. Build it at basin scale from the start, with your abstraction shown against recharge and against other users, and set up monitoring that can feed a cumulative assessment later.
What projects disclose about water, and what they leave out
Public project announcements are where communities, lenders and offtakers first look. We reviewed what four Argentine brine projects say about water on their own pages and announcements.
| Project | Province | What the public source says about water | What it does not state |
|---|---|---|---|
| Rincon (Rio Tinto) | Salta | DLE that “supports water conservation”; aims to “halve the amount of water used in processing” (Rio Tinto, 12 Dec 2024) | Baseline, freshwater source, volumes, spent brine route |
| Centenario (Eramet) | Salta | DLE plant inaugurated July 2024 at about 4,000 m, around 90% lithium recovery from the brine (Eramet, 3 July 2024) | Freshwater use, spent brine handling |
| Fénix (Rio Tinto) | Catamarca | Selective adsorption DLE; operating since 1997 (Rio Tinto) | Water source, volumes, recycling, spent brine |
| Kachi (Lake Resources) | Catamarca | Spent brine injected back into the subsurface through injection wells; a zero liquid discharge unit cuts freshwater use by about 75%; water use stated as less than 2.5% of average annual basin recharge (company statements, production EIA announcement, 26 March 2024) | Absolute freshwater volume and source |
Only one of the four expresses water use against basin recharge, which is the number a cumulative assessment needs. The others may well hold that data in their impact reports. The point is that the public story rarely carries it, and FARN’s 2019 survey in Jujuy found that 83% of community members interviewed considered the information they received too technical or too long.
A water case that holds up: checklist for a DLE project
Use this to test your own project or one you are financing.
Independent review for an Argentine water case
Brine Consulting is an independent industrial water advisory firm in Amsterdam. We sell no treatment equipment, so we can read a supplier’s DLE freshwater figure against your basin balance with no stake in which technology is chosen. For Argentine projects, handled remotely or through a defined engagement, the work covers an independent review of the water and brine balance before an IIA or DIA update, screening of eluate concentration and reject handling options from minimal to zero liquid discharge, spent brine compatibility questions, and technical input for lenders and investors through our advisory and due diligence service or as a lender’s technical advisor.
If your project also has a refinery, the effluent questions are different; see lithium refinery wastewater and ZLD. For the Chilean side of the lithium triangle, see lithium brine in Chile.
Questions project teams ask
Is spent brine reinjection required? We have not found a general rule requiring it in the laws reviewed here. Projects propose it in their impact reports (Kachi is one example), and the provincial authority assesses it there.
Where does zero liquid discharge fit in an Argentine DLE plant? Usually on the eluate concentration and reject side, where it lets the plant recycle more water. Kachi’s announcement credits its ZLD unit with cutting freshwater use by about 75%. Whether ZLD pays depends on what fresh water costs you in permits, pumping and community acceptance.
Talk through your water case
If a DIA update, a lender’s question or two suppliers’ conflicting DLE water figures are on your desk, bring them to a scoping call and we can look at what your basin balance needs to show. You can also send us your project details first.
Written by the Brine Consulting advisory team. The Brine Consulting advisory practice includes Prof. Basel Abusharkh, a senior water technology expert, industrial innovator and ZLD specialist whose work includes membrane-based technologies for recovering lithium, potassium chloride, sodium chloride and other valuable resources from seawater and industrial brines, and Juanita Ayala, Water & Climate Specialist, with more than 7 years of international experience across Latin America, Africa, Asia and Europe, whose work focuses on climate-resilient water policy and water and climate risk assessments. Meet our experts.